Belfast City Hospital- Cancer Research Centre
- Scope:
- Value:
- Client:
- Contractor:
- Consultant:
- Duration:
- Completion:
- Electrical Services
- £1.1 million
- Queen’s University Belfast
- Tracy Brothers
- White Young Green
- 18 months
- June 2007
- Six level research building consisting of general offices, laboratories, equipment rooms and plant rooms etc
- The site size was 8000m sq
- Highly serviced building which required a high degree of services, co-ordination and careful planning.
- Electrical services included; installation of an 11kV/400V transformer, 800kV generator, main and sub main switchboards, distribution boards, lighting and lighting controls, general power and mechanical wiring, IT and telephone wiring, fire alarm, CCTV, intruder alarms, door access, panic attack system and intercom, boom barriers and lighting protection.
- Project was completed on time and on budget.