Seapark – HV Infrastructure
- Scope:
- Value:
- Client:
- Contractor:
- Duration:
- Completion:
- Electrical Services
- £850k
- Amey Business Services
- Blackbourne Integrated M&E
- 18 months
- February 2009
- Operational forensic science dept, disruption kept to a minimum.
- Shut downs planned and programmed well in advance.
- Installation included a new 11kV electrical distribution system including 3No standby generator sets. Following equipment was installed:1No 5 Panel HV Panel Board, 3No 550kVA Generators, 3No LV Switchboards.
- Project completed on time and on budget